Latest Update
Construction continues on the Nashville Youth Campus for Empowerment. The project remains on schedule, with completion currently projected for mid-2027.
Recent Milestones
- Groundbreaking ceremony held on August 8, 2024
- Construction activities underway at the Brick Church Pike site
- Project top-out ceremony held on September 18, 2025
- Continued coordination among Juvenile Court, Metro Government, Bell Construction, DLR Group, and project partners